7. COMMISSIONING
7.1 PRE-COMMISSIONING CHECKS
Make sure the input switch to the Voltage Stabiliser is in the “OFF” position.
Check to ensure all the load switches are in the “OFF” position.
Before you switch “ON” the mains, visually inspect the Automatic Voltage
Stabiliser.
If dust has accumulated during installation, clean the Voltage Stabiliser thoroughly
with compressed air or with a soft brush. Should any swarf be found in the unit,
these should be removed.
Check the Ground connection, ensuring it is connected tightly.
Check all wiring connections to ensure none have worked loose during transit. As
required, tighten any loose connections.
Ensure that the incoming mains supply is available and check with a true RMS
meter that the voltage is in accordance with the particular Voltage Stabiliser
technical specification
7.2 COMMISSIONING PROCEDURE
Follow the Switch On procedure as described in Section 8.1.
Having successfully commissioned the system, please take note of the commissioning
date and bear in mind that the system should be routinely maintained on an annual
basis in accordance with the procedures laid out in Section 10.2 -
Routine Maintenance
& Service of this manual.
Adjusting the Output Voltage
The unit will have been shipped configured to deliver the output voltage as
specified by the customer at time of ordering. Should it be deemed necessary to
adjust the output voltage please refer to Section 9 – Output Voltage Adjustment in
this manual.
Activating the Over/Under Voltage & Phase Failure Protection Features
By default the Over / Under Voltage and Phase Failure protection features are
disabled. To activate these trip features, the switch (SW1) on the Servo Amplifier
PCB should be set before commencing commissioning of the unit to the “OFF”
position - see Servo Amplifier PCB drawing in the Section 9 of this manual.